The temporary location at Archer High School is located at 2250 Perry Blvd, North West, Atlanta, GA 30318.
The renovated Bunche Middle School facility will consist of a new auditorium, gymnasium, academic and support spaces, and a renovated and relocated kitchen and cafeteria. Students will also be able to enjoy a new natural grass football field that will also be used for soccer and lacrosse teams at Bunche Middle School. Additionally, the middle school will also receive a new 400 meter track, new softball field, and reconfigured parking, drop-off and bus areas.
Upcoming dates on the project timeline include:
8/09/13 Design Development
8/13/13 Project Committee Meeting #3
8/14/13 Preliminary Submittal to GDOE
8/16/13 50% Construction Documents
8/21/13 Project Committee Meeting #4